This report started as a foreman’s voice note and site photos. A person checked the quantities, then each item was costed against the project’s Bill of Quantities.
ItemQty × Rate · Amount
Excavation, foundation trenches
27 m³ × ₦8,500₦229,500
Sandcrete blocks 150mm hollow, laid
6 m² × ₦11,800₦70,800
In-situ concrete, columns and beams
0.5 m³ × ₦145,000₦72,500
Hardcore filling, compacted
15 m³ × ₦18,000₦270,000
Reinforcement, high-yield bars, cut and fixed
0.1 tonne × ₦1,450,000₦145,000
Oversite concrete (German floor), 150mm
25 m² × ₦22,500₦562,500
Sandcrete blocks 225mm hollow, laid
10 m² × ₦14,500₦145,000
verifiedValue of work today₦1,495,300
Synthetic example · Possible honeycombing. Check the column face before recording a finding.
Weather on the day: Rain, external work stopped for 2 hrs.
Signed
mic
Recorded by Musa BelloForeman · Voice note and photos, 6 Nov 2026
verified_user
Approved by Engr. Tola AdeyemiProject Manager · Checked and approved, 6 Nov 2026
This report is locked. It can’t be edited or deleted — if anything is wrong, a correction is added as a separate note linked to this report, so the full story stays visible.